Resurrection Roundabout UPDATE

Road Closure UPDATE:

29th Avenue & 35th Street Mini-Roundabout

 The project is progressing well and, beginning on Monday, April 25, 2016, the east leg of the intersection will open to traffic and the north leg will be closed.

The northerly leg will be closed from 29th Avenue to just south of Whitehall Avenue. [North Leg]

There will be a detour set-up that will direct vehicles from 29th Ave. to Indian Creek Rd.

Once that section is completed the southerly leg will be closed from 29th Avenue to the south side of 3501 29th Avenue. [South Leg]

There will be a detour set-up that will direct vehicles from 31st St. to McGowan Blvd.

Once that section is completed the entire intersection will be closed for the installation of the center island.

The total project has been allotted 45 working days to complete. (approx. 9 weeks with no weather or utility delays)